Galway Wind Park
Galway Wind Park. Four wind farms - Cloosh, Lettercraffroe, Seecon and Uggool. Phase 1 (64MW), which entered construction in Feb. 2015, is owned and financed by SSE. Phase 2 (105MW) is a joint venture between Coillte and SSE. IDL carried out the site investigation, some of which was on extremely difficult, mountainous, boggy and forested land, comprising trial pits, and boreholes. IDL also carried out on-site testing during construction of roads and hardstanding.
-
Client
-
LocationOughterard/Moycullen
-
Year2013
-
CategoriesEnergy
-